Shutdowns /Incidents/Key Developments
Since Agent Operations Began August 22, 1996
August 24, 1996-- Shutdown due to agent detection in the heating, ventilation, and air
conditioning filter bank vestibules. Possible agent release into the
environment.
September 9, 1996-- Shutdown due to complete power failure in
the plant. Possible agent release into the environment.
September 18, 1996-- Shutdown due to potentially agent-
contaminated decontamination fluid leaking through cracks in the
concrete floor into electrical room below.
September 19, 1996-- Shutdown due to Liquid Incinerator Slag
Removal System malfunction during a shakedown trial burn.
December 19, 1996-- Shutdown due to M-55 rockets jamming in
the feed gates to the Deactivation Furnace.
January 20, 1997-- Toxic spill in the 90-day storage yard
improperly cleaned up. Haz-mat team called back to the plant prior
to clean-up in "order to continue processing." Toxic material snow-
plowed against the boundary fence and left.
January 26, 1997-- Shutdown due to agent migration inside the
observation corridors of the Munitions Disposal Building. Possible
agent release to the environment.
February 6, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
February 14, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
March 13, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
March 20, 1997-- Army Project Manager, Tim Thomas admits in
Federal Court to six confirmed nerve agent stack alarms. Nerve agent
releases require shutdowns.
March, 24 1997-- M-55 Rocket campaign halted due to trial burn
failure for PCBs under Toxic Substances Control Act Requirements for
99.9999% DRE for PCBs. Public not notified until October 18, 1997.
April 10, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
April 13-14, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
April 18, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
April 20, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
April 21, 1997-- During routine maintenance alarms sound
indicating an unusually high agent reading ( > 1200TWA) inside
TOCDF.
April 22, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
April 23, 1997-- Shutdown due to "Notice of Insufficient Quality."
Army Project Manager issues notice to curtail operations due to
failure to follow operating procedures. The plant remains shutdown
until June 15 for "routine maintenance."
April, 25 1997-- Over 4,000 pages of official TOCDF documents
arrive at CWWG office showing improper analysis, characterization,
manifesting, tracking and disposal of Hazardous Waste leaving
TOCDF.
May 3, 1997-- Site masking alarm and/or stack alarm. Potential
case of chemical warfare agent release or release of other related toxic
chemicals (unidentified to date).
May 6, 1997-- Site masking alarm and/or stack alarm. Potential
case of chemical warfare agent release or release of other related toxic
chemicals (unidentified to date).
May 7, 1997-- Site masking alarm and/or stack alarm. Potential
case of chemical warfare agent release or release of other related toxic
chemicals (unidentified to date). Second occurrence on same day.
May 8, 1997-- Site masking alarm and/or stack alarm. Potential
case of chemical warfare agent release or release of other related toxic
chemicals (unidentified to date).
May 9, 1997-- Army admits to reporters that it "misled" the public about the cause of the six week shutdown.
May 13, 1997-- Site masking alarm and/or stack alarm. Potential
case of chemical warfare agent release or release of other related toxic
chemicals (unidentified to date).
May 14, 1997-- Site masking alarm and/or stack alarm. Potential
case of chemical warfare agent release or release of other related toxic
chemicals (unidentified to date).
May 15,1997-- Accusations of illegal burning of Lewisite made by
CWWG. Army first denies illegal burning then later admits to having
burned some containers that previously contained Lewisite. Plaintiffs'
evidence indicates Lewisite was burned.
May 24, 1997-- Site masking alarm and/or stack alarm. Potential
case of chemical warfare agent release or release of other related toxic
chemicals (unidentified to date).
May 28, 1997-- Citizens from Oregon and Kentucky are escorted
through TOCDF into an area with a GB-contaminated bomb casing
present. Citizens are not notified until after an anonymous call from
TOCDF notifies Utah DEQ and an OR citizen.
July 6, 1997--Shutdown due to Pollution Abatement System (PAS)
blockage. Amount of agent and other toxics emitted unknown.
August 1, 1997-- Former Chief Safety Officer, Steve Jones is ruled
for in his Dept. of Labor "Wrongful Termination Action." Judge
awards Jones his job back and $500,000 or no rehiring and $1
million. Judge calls EG&G managers "liars."
August, 1997-- Site masking alarm and/or stack alarm. Potential
case of chemical warfare agent release or release of other related toxic
chemicals (unidentified to date).
September 8, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
September 9, 1997-- Former Chief of Hazardous Waste
Management, Trina Allen wins on her discrimination part of Dept. of
Labor claim against EG&G. Allen is awarded $5,000. A Hearing on
the merits of the remainder of her claims is scheduled for December,
September 12, 1997-- Army admits, in documents sent to Utah
DEQ, that it has been burning Lewisite (L) contained in Ton
Containers of GB previously contaminated with "L," confirming
allegations made by citizen activists that TOCDF has illegally
operated.
September 14, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
September 18, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
September 30, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
October 1, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
October 2, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
October 6, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date). Second and third
occurrences on the same day.
October 11, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
October 12, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
October 16, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
October 17, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
October/November 1997-- Sources inside TOCDF (who wish to
remain anonymous) communicate to CWWG several
shutdowns/incidents at TOCDF due to computer malfunctions, slag
build-up in the PAS, numerous agent migrations within the facility,
and alarm ring-offs in the common stack, MDB and HVAC stack
(averaging 2-3 per week).
November 2, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date). Second occurrence on
the same day.
November 6, 1997-- House Government Reform and Oversight
Committee unanimously approves Human Resources Subcommittee
Report on Gulf War that concludes exposures to low-level chemical
agents (lower than the amount set as "acceptable" at TOCDF) caused
or contributed to Gulf War Illness.
November 18, 1997-- TOCDF is cited for 25 violations by the
Utah Department of Environmental Quality. Citations included
"numerous instances of noncompliance," but not enough to shut
them down, according to a DEQ spokesperson.
November 26, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
November 27, 1997-- Sources inside TOCDF (who wish to
remain anonymous) communicate to CWWG that both Liquid
Incinerators (LICs) are "down" due to malfunctions. According to
sources, one of the LICs has been down for over a month. Chronic
problems with the Brine Reduction Area (BRA) and the Pollution
Abatement System (PAS) continue to plague TOCDF.
November 30, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
December 1, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
December 2, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
December 3, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date). Second and third
occurrences on the same day.
December 5, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
December 7, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
December 20, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
December 21, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
December 26, 1997-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
January 1, 1998-- After almost 20 years of denial, a document
surfaces showing that the Army had proof as early as 1970 that the
1968 sheep kill in Skull Valley was a direct result of nerve agent
exposure by the Army. Recent depositions in CWWG federal lawsuit
disclose that Army officials have come to the conclusion that the
sheep were killed as a result of the combined effect of the nerve agent
sprayed and pesticides already present.
January 28, 1998-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
January 31, 1998-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
January 31, 1998-- Department of Labor Administrative Law
Judge, Samuel J. Smith orders EG&G to reinstate whistleblower
Trina Allen and to "cease and desist" any retaliation against her and
other employees for protected activities in the conduct of performance
of their duties.
February 1, 1998-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
February, 1998-- Worker on the hazardous waste crew discloses
that vials filled with chemical warfare agent, and having
contamination on the outside of the vials, were misplaced for a few
days. Later they were found in the toxic maintenance area. Had
these vials not been located, they would have been sent off-site as
generic waste to be disposed of at a commercial facility.
February 4, 1998-- Site masking alarm and/or stack alarm.
Potential case of chemical warfare agent release or release of other
related toxic chemicals (unidentified to date).
February 12, 1998-- According to the Deseret News, TOCDF
experienced an "all mask" alarm situation while attempting to go back
on line after a 30-day "routine maintenance" period. According to
Utah DEQ, "They (TOCDF) did confirm that this was not a false
alarm."
March 11, 1998-- Five TOCDF employees fall ill with symptoms of dizziness, headache and
nausea. Army officials say industrial materials are suspected.
March 16, 1998-- Sources inside TOCDF (who wish to remain
anonymous) communicate to CWWG that alarms have been sounding
regularly in the Unpack Area during the recently initiated MC-1 bomb
campaign. These sources also claim that workers in the area are not
wearing "Level B" protective gear as required.
March 30, 1998-- Shutdown occurrs when the metal parts furnace (MPF) overheats due to
feeding an illegal amount of nerve agent GB into the furnace. The ACAMS
alarm in the MPF duct rings off at approximately 850 times the
allowable stack concentration for agent. The ACAMS alarms in the common
stack register a large chemical spike. No DAAMS tubes are located at
the duct ACAMS to confirm for agent and no one knows if the DAAMS tubes
in the stack at the time of the incident have been analyzed to confirm
for agent. Army officials claim that agent did not go out the stack,
but can't prove that the large amount of chemical released was not
agent. The chemical plume was neither quantified or qualified.
November 21, 1998 - January 7, 1999-- There are seven instances of Unpack Area ACAMS alarms with individuals wearing inadequate protective clothing.
November 25, 1998-- Vapor leaks of GB (sarin) are detected from three 105mm projectiles.
The agent is detected while one of the projectiles is being processed
into an incinerator.
November 28, 1998-- Another vapor leak of GB is detected from a 105mm projectile which is in an on-site container.
December 4, 1998-- It is reported that 24 vapor leaks have been detected in the past two
months, all involving 105mm projectiles. Each of these 16-inch long
bullet-shaped objects contains .17 gallons of GB. 16 of the leaks were
detected after the projectiles were transferred from the storage igloos
to the incinerator building. Eight of the leaks occurred when crews
were removing a heavy bolt screwed into the nose of the projectile.
December 13, 1998-- Liquid Incinerator is shut down after 140 gallons of GB (sarin) are
spilled while being fed into the incinerator, raising serious questions
about the engineering and design of the technology.
April 13, 1999-- Shutdown occurs when TOCDF back-up power system fails after Depot-wide
outage. This failure compromised the negative air flow system, fans
leading to the stacks and other critical systems. Possible agent
release to the environment and worker exposure.
April 16, 1999-- There is confirmed agent reading in the DFS Cyclone Enclosure which is
adjacent to the outside--possible agent release to environment.
May 1, 1999-- ACAMS alarms at 508.4 twa in Unpack Area with three workers in
inadequate protective clothing. During feed stop on LIC 1, there is
ACAMS duct alarm at 1.26 asc and a stack alarm at .34 asc.
May 5, 1999-- Agent vapor leak forces workers out of certain areas within TOCDF.
May 21, 1999-- Agent migrates from a Level A to a Level C area where agent is not
supposed to be present. The ACAMS reading in the Level C area is 75
times the alarm point of .2twa. After alarm for agent presence, seven
workers have to don the masks that are at their hips and evacuate. They
are not in adequate protective clothing. Army officials testified in
federal court that they don't know if any agent escaped to the outside
environment during this incident.
May 24, 1999-- Workers removing nose closures from 105mm projectiles encounter liquid
agent in a burster well where liquid agent isn't anticipated. Workers
are not in adequate protective clothing. According to testimony of
Project Manager Tim Thomas the ACAMS rang off at approximately
1900twa--50 times the maximum level of agent for the clothing the
workers were wearing.
May 26, 1999-- Workers in the Toxic Maintenance Area are removing plastic bags of
waste when the ACAMS alarms at 1985twa causing them to evacuate. One of
the bags containing liquid agent is ripped. Again workers are not in
adequate protective clothing. Workers still ring off positive for agent
after doffing their clothing in the airlock. They then ring off
positive after being rinsed with water and still ring off positive
after a further rinsing with bleach. They have final positive readings
as they depart from the airlock.
June 4, 1999-- County-wide power outage causes TOCDF negative air flow system (HVAC)
to go down. It is 25 minutes before the emergency backup power system
comes on. Backup power is supposed to come on automatically. Loss of
the HVAC system causes agent to migrate into Level C areas where agent
isn't supposed to be. There are 3 site masking alarms during the power
outage event. Army officials testified in court that they don't know if
agent migrated to the outside environment.
June 5-June14, 1999-- TOCDF is in "Stand Down" by order of Chem Demil according to testimony
of Col. Joseph Huber in federal court. No munitions are processed
during this period while a Review Team from Aberdeen is looking at
recent agent events at TOCDF.
June 14, 1999-- TOCDF starts up after "Stand Down." Processing of M-55 rockets is
resumed. However TOCDF is shut down again because within 6 hours of
start-up, allowable feed rate for rocket processing is violated.
August 1 - September 13, 1999-- There are 19 "potential" worker exposures. 4 are in Level B clothing.
11 are due to rips in protective ensembles or gloves and 4 workers are
present in over 500 IDLH atmosphere.
August 9, 1999-- Tangled air hoses prevent DPE entrants from reaching egress air locks.
August 9, 1999-- Worker exposed to nerve agent with tear in protective suit not seen at clinic until three and a half hours later.
August 25, 1999-- ACAMS in Unpack Area alarms at .21 twa. The ACAMS heat trace is discovered to be burning.
Week of Aug. 31-Sept. 4-- DFS feed chute gets jammed with rocket pieces. Site team shuts down DFS
to change out warped section of feed chute. Angle irons used to
dislodge previous jam get jammed in chute also.
Week of Aug. 31-Sept. 4-- Internal report blames cracks in concrete floor of MDB for decon
seepage into electrical room and states that new cracks continue to be
identified.
September 9, 1999-- Cleanliness and organization of toxic areas is so bad that processing
is shut down for 59 hours to get housekeeping issues straightened out.
September 20, 1999-- Internal report states that SOPs are happening too quckly for people to
keep up and more often than not, new SOPs are not being carried out.
September 21, 1999-- Internal report reveals that workers are performing unapproved SOP of
hitting wooden pallets with a steel mallet to loosen pallet covers
which results in projectiles falling from pallets onto to UPA floor.
September 23, 1999-- Internal report blames poor contamination control and inadequate
decontamination attempts for high levels of contamination in airlocks.
September 27, 1999-- Control room operator discovers that two "pressurized" ton containers
have been in the 90-day storage site for greater than the allowed time.
Report of incident states that information transmitted to management
after discovery of tons is "less than adequate,...training received on
environmental inspections is inadequate." Incident results in a
Government Nonconformance Report and an EG&G Deficiency Report.
November 3, 1999-- Manager orders worker to make DPE entry against advise of monitoring
team who informed him of questionable ACAMS reliability in hot area.
November 3, 1999-- TOCDF system engineer calls LIC slag removal system "fatally
flawed"--engineers have to "jumper" the system code to get the system
to operate correctly.
November 3, 1999-- ACAMS alarm of .37 in LIC Secondary room goes unnoticed for 2 hours during which time several workers enter the room.
November 9, 1999-- ACAMS in EHM alarms at 1.23 twa with unmasked workers present.
Personnel are told to exit into airlock but are not told seriousness of
situation and are not told to mask.
December 6, 1999-- The protective suits of two workers are melted during slag removal operation in one of the liquid incinerators.
December 7, 1999-- In a fire in the upper gate of the deactivation furnace feed chute,
three rocket sections burn. Flames are also seen on the floor and at
the shear blade. The time of the fire is uncertain "due to
unreliability of the fire sensor." Instructions have been given to
avoid leaving rocket sections on the upper gate "even if it means
burning them in the chute." Three hours earlier, the lower gate
malfunctioned and resulted in a stop feed. It takes ten days to prepare
report on the incident.
February 20, 2000-- Two workers exposed to nerve agent GB when it leaks into room where they are working.
February 23, 2000-- 40 to 45 gallons of molten slag spills from a drum and starts a fire
that burns the covering of the concrete floor and electrical equipment
in a secondary room of the liquid incinerator.
April 30, 2000-- A maintenance man just happens to walk past the Cyclone Ash Bin
Enclosure of the Deactivation Furnace (DFS) and notices smoke, heat and
a bulged out door. There is a fire going on that no one had detected.
The fire ignites and decomposes the charcoal in the filter system of
the Ash Bin and would have entered the filter banks of the MDB if it
hadn't been discovered by a worker out for a walk. The fire was
precipitated when the blind flange was installed in preparation for an
entry into the DFS to clear a jam in the Heated Discharge Conveyor.
May 8, 2000-- After workers finish maintenance on deactivation furnace feed chute
there is confirmed release of nerve agent GB out of common stack into
environment at 11:26 pm. Army reports that afterburner was blown out
due to malfunction of air flow meter which was clogged with liquid.
Stack alarm rings off for about 20 minutes at somewhere between 3.7 and
8.6 times the allowable stack concentration of GB. Army reports on the
alarm reading are inconsistent. Mysteriously, after stack alarm rings
off, alarm in furnace duct leading to stack rings off for agent
presence. Facility managers say they have no clue as to why sequence of
alarms was apparently backwards.
May 9, 2000-- A confirmed release of GB to the environment takes place at about 1:15
am (less than an hour and a half after the confirmed release May 8)
when workers attempt to relight deactivation furnace afterburner. Local
emergency officials not notified until four hours after first GB
release. Decision made by Army manager not to immediately notify local
officials is in violation of Army SOPs, facility's operating permit
granted by State of Utah and agreements with local emergency
responders. Facility is shut down until investigation team, headed by
the Army, makes final report on the incidents. EG&G manager
predicts investigation will lead to physical modification, not just new
SOPs. Shut down could last several weeks.
June 6, 2000-- TOCDF is still shut down. It is reported that the facility's shut down
is costing about $285,000 per day--totaling almost $8 million to date.
July 26, 2000-- TOCDF has been shut down for 79 days. At $285,000 per day--the cost so far is more than $22 million.
July 28, 2000-- The Utah DEQ authorizes the restart of the two liquid incinerators and
the metal parts furnace after the entire facility had been shut down
for 81 days following the May 8-9 agent releases.
September 19, 2000-- The Utah DEQ authorizes the restart of the DFS after it had been shut down for 133 days following the May 8-9 agent releases.
October 19, 2000-- At the Utah CAC meeting, it is stated that there had been 97 agent
alarms at TOCDF since May 8. 14 of the alarms were in the common stack.
November 16, 2000-- At the Utah CAC meeting, it is stated that there had been 41 agent
alarms at TOCDF since October 19. Three of the alarms were in the
common stack and five were in ducts leading to the common stack.
November 25, 2000-- The nerve agent GB (sarin) is detected in employees' work clothes. The
workers come in from inspecting filters outside in cold weather and
apparently the sarin begins vaporizing as their clothing warmed up.