CWWG

GAO Report:  Chem Demil Program "Remains in Turmoil"


Chemical Weapons Working Group
PO Box 467, Berea, KY  40403
(859) 986-7565  fax:  (859) 986-2695
www.cwwg.org

for more information: Craig Williams:  (859) 986-7565
or 302-1103  (cell)

GAO REPORT: CHEMICAL DEMILITARIZATION PROGRAM
"REMAINS IN TURMOIL"

 Incineration problems include: “plant safety issues; difficulties in meeting environmental permitting requirements;  public concerns about emergency preparedness and budgeting shortfalls"

The Government Accounting Office (GAO) today (Sept. 5) released another in a long series of reports severely criticizing the Army's Chemical Demilitarization Program.  Focused primarily on the management and the "lack of sustained leadership" within the program, the report also identifies what many have long held to be the root cause of the program's failures--a bad technology choice for disposal:  incineration.

The report says, "Nearly all of the incineration sites will miss DOD-approved 2001 schedule milestones because of substantial delays that stem from a number of problems that DOD and the Army have not been able to anticipate or influence."  These include: "plant safety issues; difficulties in meeting environmental permitting requirements; public concerns about emergency preparedness and budgeting shortfalls."

Craig Williams, director of the Chemical Weapons Working Group (CWWG), a national anti-burn coalition, "The fundamental problem stems from the fact that the Army's decision to use incineration was wrong in 1982 when they chose it, and remains unworkable today."

But the report also said that "Although the neutralization sites have not missed their milestones yet, they too have experienced delays."  Earlier this week the CWWG issued a press release stating that the only operating neutralization plant, in Aberdeen Maryland, would soon be shut down for approximately a month for engineering modifications.
    
"The difference," according to Williams, "is that the one neutralization plant has only been operational for 6 months, while the incineration plants have been collectively trying to operate for 17 years. One would expect some short delays in a first generation plant, but to have consistent delays, often for months at a time, after an approach [incineration] has been used for almost two decades should tell us something about their reliability."
    
The GAO also noted that the DOD increased the 2001 cost estimate for the program--$24 billion--by an additional $1.2 billion and that, "other factors, yet to be considered, could raise these estimates even more."  The original 1985 estimate, for the entire disposal program, was $1.83 billion.
    
Regarding DOD and Army policy and guidance documents, the GAO said, "all documents were out of date and did not reflect changes to the program."  They also found that "Neither DOD nor the Army has adopted a comprehensive risk management approach to mitigate potential problems."  It further states that delays at incineration sites have resulted from various "long-standing" issues because the Army, "does not have a process to identify and mitigate them [problems]."
    
The Army often touts it's "Lessons Learned Program" to the public as the primary means to avoid repeating the same mistakes and problems that have occurred at incinerators in the Pacific and Utah.  The GAO report however exposes the distance between the Army rhetoric and its execution.  The GAO says, "An effectively managed program would have an approach such as lesson learned, to identify and mitigate issues."  But, "....the Chem-Demil Programmatic Lessons Learned Program has been shifted to individual contractors from a headquarters centralized effort.  By decentralizing the program, it is uncertain how knowledge will be leveraged between sites to avoid or lessen potential delays due to issues that have previously occurred."
    
Williams said, "It's sad - but not surprising - how the incineration program's Public Information Office has never mentioned this to citizens in any of the communities."  
    
The report concluded by saying, "...the program continues to flounder" noting the program's, "continued instability, ineffective decision making and weak accountability."
    
According to Williams, "This program, when measured against any criteria point - safety; agent containment; environmental compliance; worker protection; cost or schedule, fails each.  Yet the Army insisted on firing up the incinerator in Alabama last month, while simultaneously breaking their promises to provide protective capabilities for schools and the handicapped there should an event occur.  It appears the worse things get, the more desperate they [Army] become to burn these weapons.  How many reports will it take before the Pentagon or the Congress will take the actions necessary to prevent a disaster?"

--30--           












CWWG

CWWG Home Page

Contact us:
Chemical Weapons Working Group
Kentucky Environmental Foundation
P.O. Box 467
Berea, KY 40403
phone: 859-986-7565
fax: 859-986-2695


For comments about this WWW page contact Lois Kleffman.