Hermiston Herald A-1, Oct. 11, 2002:
Safety procedures modified at depot
By Frank Lockwood
Staff writer
HERMISTON - Umatilla Chemical Agent Disposal Facility is subject
to modified
safety procedures, in part due to the investigation of a worker's
accidental
exposure to GB nerve agent at the Tooele Chemical Agent Disposal
Facility
(TOCDF) in Utah.
The investigation summary answers some questions, raises others.
For
example, why did the contractor apparently ignore known potential
sources of
leaking GB? On July 15, 2002, Tooele workers were performing
routine maintenance when
air monitors in the immediate area detected GB nerve agent. One
worker
tested positive for exposure to chemical agent during the maintenance
procedure. The worker was decontaminated and placed under medical
observation. He was cleared to return to work the following day.
Immediately after the event, PMCD halted all operations at
the facility
except those necessary to maintain safe and stable conditions,
and the Army
launched an intensive investigation to determine the cause of
the accident,
implement corrective measures and prevent any future occurrences.
The safety improvement program directs PMCD and its systems
contractors to
maximize efforts to promote a universal safety culture among the
plant
workers, improve communications and coordination among engineering,
safety,
operations and maintenance personnel to improve the internal processes
to
share lessons learned at the facility; and ensure all future operations
plans include the proper checks and balances to provide maximum
worker
protection. A corrective action plan that responds to the recently
completed
Army Board of Investigation Report is being separately prepared.
The goals of the safety improvement program are to assure worker
safety,
protection of the environment and compliance with applicable laws
and
regulations. Measures have been identified which will be incorporated
not
only at the TOCDF, but at every future disposal site to ensure
that this
type of event does not occur again.
"The improvements identified following the Tooele event
are being adopted at
Umatilla," said Don Barclay, Army site project manager at
the Umatilla
Chemical Agent Disposal Facility. "Safety remains our top
priority."
Some of the safety issues identified at Tooele were reported
by a Board of
Investigation. The board was established in July, 2002, by the
assistant
secretary of the Army for Installations and Environment, and produced
a
summary of events surrounding the Tooele accident. Parts of the
sequence of
events revealed in the summary are as follows:
Liquid Incinerator 1
- Spring 2001: A pressure regulator was causing emissions problems.
The
problems occurred whenever one collection tank was drained empty,
and the
system was therefore switched over to draw agent from another
tank. When
those switch-overs happened, monoxide levels exceeded allowed
limits. An
engineering change was subsequently made to modify the pressure
regulator,
in order to purge lines of agent at lower pressures, and thus
eliminate
monoxide "spiking" in the emissions. The regulator
was modified and
installed.
- January 2002: High levels of agent GB were detected in an
area where the
agent was not supposed to be. using remote cameras, control room
operators
identified the source of agent leakage: GB was observed dripping
from the
newly installed, modified air pressure regulator.
· Through engineering observations and analysis, it was
determined that two
check valves and a "block valve" in the backflow isolation
devices were
"frozen" in the open position and could not be repaired.
·
- Feb. 5, 2002: The PMCD Field Office sent a formal advisory
letter to the
System Contractor's Plant Manager, cautioning that the modification
of the
LIC 1 Primary air pressure regulator had been approved and was
being planned
for LIC 2 Primary and that measures should be taken to validate
the
integrity of the check valves and block valve. However, the System
contractor did not respond to the letter, nor was it placed in
the System
Contractor's action tracking system or correspondence control
tracking
system.
·
- Neither the System Contractor nor PMCD Field Office personnel
provided
notification of the incident to PMCD's centralized lessons learned
database.
Liquid Incinerator 2
·
- Spring 2002: Work began to modify the pressure regulator
for LIC2 Primary.
No steps were included to verify the integrity of the two check
valves and
block valve, as previously suggested by the PMCD Field Office.
The Work
Order prepared by the LIC System Engineer did not mention the
prior incident
involving migration of agent into the LIC 1 Primary purge air
regulator and
the potential for a similar situation on the LIC 2 Primary.
·
- July 15, 2002: Two maintenance workers entered the LIC 2
Primary Room
wearing full face industrial respirators approved by the National
Institute
of Occupational Safety and Health, overalls, and leather boots
and gloves,
do install the modified air pressure regulator. They were loosening
couplings with a wrench and by hand for a three-foot section
of purge air
line containing the air pressure regulator when a portable GB
Monitor alarm
went off. They removed their industrial respirators and donned
their
government respirators. During the change of masks, some of the
contamination from the leather glove of the worker who had handled
the pipe
was transferred to his head, hair, and/or respirator. The two
workers were
moved to a room called LIC 2 Secondary Room for assessment.
- During their assessment in the LIC 2 Secondary Room, problems
arose
regarding the monitor readings. About an hour after the initial
alarm, the
two maintenance workers were released from the LIC 2 Secondary
Room, based
on the inaccurate perception that they had cleared at least two
monitoring
cycles. They unmasked and were transported to the medical clinic
without
having undergone decontamination or preliminary medical evaluation.
When
they arrived in the Clinic's Decontamination Vestibule, however,
alarms
indicated that one or both of them were contaminated.
·
- The two maintenance workers spent about four hours in the
Decontamination
Vestibule undergoing repeated decontamination cycles before they
were
declared free of contamination and brought into the Clinic Treatment
Area
for evaluation. Atropine was not administered, but a doctor observed
one of
the workers to have experienced miosis (reduction of the eye
pupil). Later
it was learned he also experienced disorientation, headaches,
blurry vision,
tightness in the chest and a runny nose, but he did not report
these
symptoms to the medical staff while he was in the Clinic Decontamination
and
Monitoring Vestibules and under observation. Later blood analyses
indicated
a 25 percent depression of red blood cell cholinesterase from
the worker's
baseline. The miosis and red blood cell cholinesterase depression
are
indicative of exposure to GB.
Army and PMCD personnel directed the Hermiston Herald to Greg
Mahall in
Maryland as the person most familiar with the Tooele situation.
We called
and faxed messages to Mahall in the early afternoon but he was
not able to
respond before we went to press. Some of the questions we presented
were:
- Were the check-valves mentioned as "frozen" deliberately
altered or
disabled?
- When was it first known that the check-valves were not functional?
- Why didn't the system contractor respond to the PMCD's Feb.
5 letter which
advised them to validate the operation of the check valves?
- Why wasn't the PMCD letter concerning the check-valves placed
in the
system contractor's tracking system?
- Why weren't steps taken to verify the integrity of the two
check valves
and the block valve?
Mahall was not available, and his boss, Marilyn Daughdrill,
said she did not
know the answers to our questions. Program Manager for Chemical
Demilitarization staff was checking to see who might have that
information,
she said.
A copy of the safety improvement program and an executive summary
of the
Army Board of Investigation Report can be obtained by contacting
or visiting
the Umatilla Chemical Disposal Outreach Office at (541) 564-9339,
190 E.
Main, Hermiston, Ore., 97838.
n Frank Lockwood may be reached at 567-6457 or by e-mail at
flockwood@hermistonherald.com.