Delays likely at
arms plant
Depot should finish burning chemicals by '08
By Lee Davidson
Deseret Morning News
WASHINGTON — The Army warns that more delays are
possible for its embattled program to destroy chemical arms, which is already
years behind schedule and has skyrocketed in cost from $1.7 billion to $25
billion.
It says it still hopes to complete all arms destruction
by 2011 — or four years beyond the current 2007 deadline set by international
treaty. That treaty, however, allows one five-year extension to 2012.
Of Utah note, its Deseret Chemical Depot originally
stored 44 percent of the nation's stockpile of chemical arms, or 13,616 tons.
The Army reports that Deseret has incinerated about 44 percent of its stockpile
so far and is scheduled to destroy all of it by February 2008.
Despite the extension of the deadline, the Deseret
Chemical Depot expects to have 100 percent of stockpiled agents destroyed
by 2008, said depot spokesman Chuck Sprague, barring any unforeseen delays.
Sprague said the depot is currently destroying the
nerve agent VX, and will complete VX destruction by as early as late summer
2004. After that it will take several months to retool the facility to begin
destruction of mustard agent, which is a blistering agent. Sprague said despite
having incinerated 44 percent of its stockpile, the Deseret Chemical Depot
still holds the nation's largest stockpile.
"We will get this job done no matter what challenges
we face," said Michael Parker, director of the new Chemical Materials Agency,
which combined various agencies with overlapping jurisdiction to try to help
streamline arms destruction oversight.
While he told the U.S. House Armed Services Committee
on Thursday that new, more realistic projections show chemical destruction
at all eight destruction sites nationally is possible by 2011, challenges
are looming that could cause additional delays.
For example, he said the Centers for Disease Control
and Prevention issued new, lower limits for airborne exposure to nerve agents
(which Deseret is in the process of incinerating).
"These new more stringent limits will require us to
monitor for these chemical agents at much lower levels than we have previously,"
Parker said.
"Although we have technology that is capable of detecting
chemical agent at these extremely low levels, it is proven only in a laboratory
environment and application to a plant setting will be problematic," he said.
"Under operating conditions, there are many chemicals
that are not chemical warfare agent that interfere with chemical agent monitors.
The lower our monitoring levels, the higher the probability of of interference
that causes false alarms. More false alarms slow operations and lower confidence
in the monitoring program," he said.
"We are working to meet this challenge," Parker added.
Patrick J. Wakefield, deputy assistant to the secretary
of Defense, added that several other challenges loom that could bring more
delays.
"New environmental permitting and monitoring requirements
can influence our program," and requirements for emergency preparedness programs
in communities near destruction sites are growing, he said. "We also face
continued opposition from special interest groups through litigation."
He also warned that "accidents and safety incidents
may occur, sometimes crippling our destruction efforts." For example, when
a plant worker at Deseret came into contact with nerve agent during routine
maintenance, that plant was shut down from July 2002 to March 2003 to find
causes and implement corrective action.
"I want to emphasize . . . that our primary consideration
is safety to the public as well as the work force," Wakefield said.
Wakefield and Parker pleaded for full funding for
the arms destruction program, saying lack of funding has also contributed
to delays through the years.
Wakefield also said that just last week, an international
board approved extending a deadline for the United States to have completed
destroying 45 percent of its agent from 2004 to 2007. Wakefield said he is
confident that new deadline can be met.
He said the United States plans to ask later that
the deadline for completing all chemical destruction be moved from the currently
required 2007 to 2012. Current schedules, if worried-about delays do not
materialize, would allow just barely meeting that extended deadline.
The General Accounting Office, a research arm of Congress,
reported that other nations are also having trouble meeting the deadlines.
Russia, for example, has missed all its deadlines so far, and only began
destroying its stockpile last December.