deseretnews.com
Utah


Monday, February 19, 2007

Arms destruction drags

By Lee Davidson
Deseret Morning News


Congress originally ordered destruction of all U.S. chemical arms by 1996 and thought it would cost $1.7 billion. Recently, after a long string of revised estimates, the Army projected it will really cost $27.8 billion and not be finished until 2023.
     
Now, Pentagon inspectors worry even that may be too optimistic. They say big delays and cost overruns "will likely continue, making it difficult or impossible for the program to meet scheduled deadlines" -- unless significant changes are made.
     
That is according to a report issued five months ago by the Army Audit Agency. The Deseret Morning News just obtained the report through a Freedom of Information Act request.
     
The report complains that contracts inadvertently reward contractors for delays and that contractors often receive performance bonuses when not earned. The Army also fails to investigate whether past delays and overruns will likely repeat, and it often fails to incorporate lessons from problems into projections for later work, the document said.

The findings are important to Utah, home of Deseret Chemical Depot and its Tooele Chemical Agent Disposal Facility. Before incineration of arms began at the disposal site, the depot stored 44.5 percent of the nation's chemical-arms stockpile -- with smaller amounts scattered at eight other facilities nationally.
     
As of Feb. 7, the depot had destroyed 58 percent of its original stockpile. Pentagon budgets project continued funding for destruction work there through 2016 -- although work schedules estimate the destruction could be completed there as early as 2012. Work at other bases could last until 2023.
     
Pentagon inspectors wrote that program projections may be too optimistic -- mostly because the Army is not keeping close enough watch on contractors running destruction plants, nor giving them enough incentives to complete work on time.
     
In fact, inspectors say, the Army is doing the opposite -- inadvertently giving contractors financial incentives to delay.
     
In part, they said, that is because contracts now cover their costs plus extra fees for administration. The longer facilities operate, the more contractors make -- even if they miss some bonuses designed to reward on-time and environmentally sound work.
     
"Contractors had little incentive to -- and weren't sufficiently penalized for failing to -- prevent or minimize cost and schedule growth," inspectors complained.
     
They said they found that incentive bonuses for on-time and safe work are often given anyway, even when not earned, making the situation worse.
     
For example, the contractor running a destruction plant in Pine Bluff, Ark., received 87 percent of available award fees for four years, despite continuing, significant delays.
     
"One delay extended the originally scheduled April 2004 start of operations date to February 2005, because the contractor wasn't able to hire a sufficient work force," auditors wrote.
     
Similarly, they complained that contractors were sometimes rewarded for environmental compliance when they did not meet the required goals.
     
For Tooele to receive such bonuses, it was supposed to achieve a numerical rating of 61 or above for environmental compliance in 2002 and 70 or above in 2003.
     
However, it received only "ratings of 38.96 and 65 respectively, yet still earned an award fee above the base fee," the report said.
     
"By not withholding award fees from contractors who didn't control costs and schedules" or perform well environmentally, the Army "may have signaled that they didn't view cost and schedule containment as a top priority," the auditors noted.
     
Inspectors complained that while reasons for delays and overruns were generally known, the Army "didn't fully ascertain, investigate or report the likelihood that similar delays and increases would recur"-- making budgets and schedules shaky.
     
Auditors said Tooele expected to require only four months to change over from processing arms filled with nerve agent GB to those filled with VX. But it actually took more than a year.
     
"Yet site managers continued to report an estimated five-month time frame to complete their next agent changeover from VX to mustard agent," the auditors complained, saying Tooele should have expected it to take longer.
     
Worse, the report said, managers at other facilities "didn't adjust their agent changeover schedules to incorporate the actual experience gained at Tooele." Inspectors complained the Army never asked contractors to explain why they didn't adjust schedules and cost estimates.
     
They added that because no state-based facility "has completed an agent changeover within schedule ... managers should direct all facility managers to reassess current changeover schedules," the report said.
     
Inspectors also complained that the Army never held contractors responsible for delays or cost overruns that were their fault, and often failed to investigate them well.
     
They complained official reports used only vague wording to explain overruns. For example, to explain why operations at Pine Bluff cost $1.6 million more than expected in one period, an Army report said merely that it was from the "impact of using additional resources" without giving details. That also made it more likely that problems could recur.
     
Similarly, inspectors complained that the Army was not ensuring that contractors responded well and quickly to state notices of environmental violations, nor ensure for itself that problems were corrected -- which could also lead to delays and overruns.
     
It said that happened even though regulators in Utah, Oregon and Alabama had sent notices of such problems as "processing hazardous materials with disabled instrumentation," "failing to notify the state of system modifications," and "storing hazardous waste for more than 90 days without a permit."
     
Auditors said delays and overruns will continue unless oversight improves and contracts are revised to do away with inadvertent incentives for delay. They called for possibly paying a flat fee per munition destroyed.
     
They noted that similar calls for better oversight had been made for years by a variety of inspecting agencies, but delays and cost overruns have continued.
     
In its official written response to the audit, the Army said that its Chemical Materials Agency has taken steps that "meet the intent" of auditor recommendations, and it considers issues raised in the report to be resolved.
     
The Army also said said the CMA said is pursuing "shared-savings contracting mechanisms to better reward contractors for exceptional cost and schedule performance."