Defense Environment Alert
September 9, 2003
GAO: CHEMICAL WEAPONS DISPOSAL PROGRAM 'CONTINUES TO FLOUNDER'
The Pentagon's chemical demilitarization program "continues to flounder"
-- despite several reorganizations of its complex structure -- and continues
to face increasing costs and schedule delays, the General Accounting Office
(GAO) finds in a new report. GAO is recommending that the Defense Department
and the Army develop an overall strategy and implementation plan for the
program, as well as employ a risk management approach that would anticipate
potential problems for the program rather than continuing in crisis mode.
DOD is concurring with the recommendations, saying it is in the initial stages
of developing an overall strategy and implementation plan that it will complete
in fiscal year 2004. Additionally, DOD says an Army agency is in the process
of reviewing several components of a risk management approach.
The Sept. 5 report, Chemical Weapons: Sustained Leadership, Along With Key
Strategic Management Tools, Is Needed to Guide DOD's Destruction Program,
is the just the latest GAO study since the mid- 1990s to find shortcomings
with the chemical demilitarization program. The House mandated the GAO investigation
in its report plan to guide the program and monitor its progress, GAO says.
The report is particularly critical of the program's reliance on acquisition
guidance because the program has non-acquisition elements, and it notes that
all documents GAO reviewed were out of date and did not reflect changes to
the program. While the Army and DOD say CMA is developing an updated strategy,
GAO says a draft version is still not comprehensive because it fails to address
all the components of the program, such as emergency preparedness.
Additionally, the chemical demilitarization program lacks a risk management
plan. The Army drafted one in June 2000, but it never formally approved or
implemented the plan, the report says, adding that DOD and Army officials
have given several reasons for not having such a plan.
"A DOD official indicated that the approach that has been used to address
program problems has been crisis management, which has forced DOD to react
to issues rather than control them," the report says. "The deputy program
manager stated that the program's focus has been on managing individual sites
by implementing initiatives to improve contractor performance as it relates
to safety, schedule, and cost. The official also said that establishing a
formal, integrated risk management plan has not been a priority." Another
program official told GAO the infrastructure is in place to finalize such
a plan by October, when CMA takes over official leadership of the program.
But GAO says the status of this effort is unknown.