Defense Environment Alert
an exclusive biweekly report on defense policies
for cleanup, compliance and pollution prevention
Vol. 12, No. 12--June 15, 2004
DOD-ORDERED AUDIT PROBES PUEBLO FACILITY'S ACCELERATION PLANS
At the behest of the Pentagon's top acquisition official, DOD's
inspector general (IG) is auditing the growth in scope of the chemical demilitarization
project at the Army's Pueblo, CO, facility, and how influential the facility's
contractor has been in determining the size of the project. But environmentalists
say the program at Pueblo is being investigated and chastised by the acquisition
office "for doing what they were told to do" - accelerate destruction of chemical
weapons.
"I am concerned with the growth in scope of the project, and by the amount
of discretion that may have been ceded to the contractor to determine the
project requirements," Acting DOD Acquisition, Technology & Logistics
Under Secretary Michael W. Wynne says in a May 14 memorandum to the IG requesting
the audit. Wynne cites significant growth from the original estimate for the
project, compared to the current plan. The plant staff level rose from 587
to 1,100, the processing area from 95,000 square feet to 240,000 square feet,
and the cost from $1.6 billion to possibly hundreds of millions of dollars
more, he says.
"Based on the changes in scope to include the increased contractor staffing
levels and the space requirements for the chemical disposal processing facility,
we question the reasonableness of the project life cycle costs." The memo
is available on InsideEPA. com. See page 2 for details.
The Assembled Chemical Weapons Alternatives (ACWA) program is overseeing
the design, construction and operation of a chemical weapons neutralization
pilot plant to destroy the chemical munitions stored at Pueblo. DOD officials
backed neutralization over the Army's baseline incineration method two years
ago, and awarded Bechtel National Inc. the contract.
Wynne asks the IG to address any deficiencies in the acquisition process
for the plant, particularly "[w]hether the government's contractual relationship
with the systems contractor has contributed to the growth in the life cycle
cost of this facility," the handling of the public affairs contract, whether
the use of an accelerated contract approach has effectively controlled cost
increases, whether the use of a performance-based contract has been an impetus
to build a larger facility, "[w]hether this contracting approach may have
operated to eliminate Department-approved acceleration efforts," and the reasons
for the increase in staff levels and processing area.
But Craig Williams, director of the citizens coalition Chemical Weapons
Working Group, is calling the audit request a "witch hunt" and an attack
on the ACWA program, saying Wynne's letter seems to be "almost accusatory."
If the contract has to be re-bid due to the audit, it could delay the program
by a couple years, he says.
At the direction of DOD's acquisition office - the same office now requesting
the audit - ACWA proposed an accelerated destruction plan for Pueblo that
looked to perform certain tasks simultaneously, rather than sequentially.
The acquisition decision memorandum (ADM) signed by Wynne's predecessor, E.C.
"Pete" Aldridge, on July 16, 2002, endorsed neutralization followed by biotreatment
and called for expedited disposal of the stockpile due to national security
concerns. And a DOD record of decision similarly called for acceleration,
Williams says.
When ACWA produced the acceleration plans, the DOD acquisition office gave
no feedback, so ACWA executed the plans, he says. But now the program is being
investigated for following orders, he contends. Williams believes it is "not
appropriate" for the acquisition office to essentially set new policy, through
the audit request, contrary to the ADM.
DOD overseers of the chemical weapons program expressly questioned acceleration
plans late last year, and asked ACWA to submit other options for the design
of the destruction facility. "While we directed accelerated destruction of
the Pueblo chemical weapon stockpile, current information indicates the emerging
design concept is not executable," wrote Dale Klein, an assistant to the secretary
of defense on nuclear and chemical and biological defense programs, in a
Dec. 22, 2003, letter. Even though it asked for acceleration, DOD has an
issue with the affordability of the plant, an ACWA source says. Facing cost
overruns at other facilities, DOD proposed distributing nearly all of the
planned funding for Pueblo in fiscal year 2005 to other sites (Defense Environment
Alert, Feb. 10, p4).
Williams believes ACWA's success is being penalized, noting the speed with
which the program has been moving in the permitting process, compared to the
incineration plants in other states. He says DOD, expecting a slower process,
may have thought the Pueblo program would not need the funding so soon.
But a DOD spokeswoman in response to questions submitted by Defense Environment
Alert says that acceleration options that the program first considered, such
as a quicker contract award and expedited permitting process, "were intended
to lower cost, schedule, manpower, and processing facility size." Some of
these have done this, while others could not be implemented.
DOD's acquisition office concedes it never signed off on the acceleration
design plans for Pueblo, but that the growth in scope was detected during
a standard program review and DOD then analyzed "design concept variants to
determine the viability of more cost effective options that do not sacrifice
safety or schedule," the response says.
DOD contends it did not expect to see a larger facility, more workers and
higher costs under an accelerated plan. But the ADM from July 2002 talks of
endorsing potential increases due to acceleration. "Acceleration options approved
during the current Defense Planning Guidance Review that require additional
funding will also be programmed in the FY 04-09 Army Budget Estimate Submission,"
the directive reads.
The main design change now being examined is to go from three processing
lines down to two, the ACWA source says. That would obviously lengthen the
schedule, but lower upfront capital costs for construction, the source says.
The program will take several more months to determine the cost and schedule
impact of adopting such design changes, the source says. The audit request
grew out of this re-analysis, the source says.
The source says ACWA is complying with all requests and working with the
IG to resolve any issues. The questioning, however, has not halted the initial
work that is taking place for the plant's development, the source says.
Williams says that while acceleration will cost more upfront, it would cut
down other costs, including storage and operational time. DOD's push to abandon
acceleration is to get short-term justification in a fiscal year or two in
order to try to save dollars, with no long-term vision of what the objective
is, he says.
And a Sierra Club source says the increases in project cost under acceleration
are small when compared to the decreases in storage costs and other risks
if acceleration is not applied.