Defense Environment Alert
an exclusive biweekly report on defense policies
for cleanup, compliance and pollution prevention
Vol. 12, No. 7--April 6, 2004
U.S. MAY MISS 45 PERCENT CHEMICAL WEAPONS DESTRUCTION
Despite assertions otherwise from Pentagon officials, it is "questionable"
whether the United States will meet aninternational treaty's extended deadline
to destroy 45 percent of the nation's stockpile of chemical weapons by December
2007, according to the General Accounting Office (GAO). And unless the chemical
demilitarization program "is able to resolve the problems that have caused
schedule delays," the United States also risks missing an extended 100 percent
destruction deadline of 2012, GAO told a House panel April 1.
But Army and DOD officials countered GAO's conclusions on the 45 percent
destruction deadline, maintaining they can meet it.
GAO's Director of Defense Capabilities and Management Raymond Decker, in
testimony before the House Armed Services terrorism, unconventional threats
and capabilities subcommittee, also raised concerns about spiraling costs
for a community emergency preparedness program the Army funds. Communities'
requests for funding in fiscal years 2004 and 2005 have exceeded approved
military budgets by $88 million, Decker said. "These unfunded requirements
have caused further delays in overall program operations because funds have
to be diverted from other sites' approved budgets to pay for these communities'
requirements," he said.
As of March, the Army has destroyed 27.6 percent of the original chemical
weapons stockpile, but GAO also noted that very little agent destruction
- about 1.5 percent of the total - has been destroyed over the past six months.
In response to a question from Rep. James Langevin (D-RI), Patrick Wakefield,
deputy assistant to the secretary of defense for chemical demilitarization
and counterproliferation, said the penalties for not meeting the treaty's
final 2012 deadline are undefined, and noted that Russia has only destroyed
I percent of its stockpile to date. Wakefield also said that because the
United States received an extension to meeting the original 45 percent destruction
deadline, "in principle, the United States has received an extension to 2012"
for the 100 percent deadline. The Chemical Weapons Convention requires parties
to completely destroy their stockpiled chemical weapons by 2007, but allows
parties to request a five-year extension to that deadline.
Start-up of incinerators at Umatilla, OR, and Pine Bluff, AR, remain behind
schedule, according to GAO. Last fall, the Army estimated Umatilla would
begin operations in March 2004 and Pine Bluff would begin destroying weapons
in April 2004, but GAO said those estimates have slipped to July for both
sites. Relevant documents are available on InsideEPA. com. Seepage 2 for
details.
Additionally, bulk agent neutralization sites at Aberdeen, MD, and Newport,
IN, have missed scheduled milestones under an accelerated destruction schedule,
put in place after the Sept. 11 terrorist attacks. Although Aberdeen has
shaved off four years from its original agent destruction timeline - even
with the delays - GAO said the hardening and congealing of residual mustard
agent in the ton containers will require additional operations. Dale
Klein, assistant to the secretary of defense for nuclear, chemical and biological
defense programs, said it turns out the so-called "speedy neut" efforts at
Aberdeen will save time on demilitarization activities but not cost.
Newport is now scheduled to begin destroying its stockpile of bulk VX agent
in August, but the military's plan to ship secondary waste to New Jersey
for treatment has not been finalized and faces opposition from residents,
workers and environmental groups, GAO said.
These delays have increased the cost of the chemical demilitarization from
$15 billion in 1998 to $24 billion in 2001. DOD told GAO last fall that costs
had increased to $25.5 billion, "and this estimate is certainly going to
rise further, given the information we obtained on schedule delays from fiscal
year 2005 budget documents and from program officials," GAO said. Program
officials will present new cost estimates to DOD in preparation of the FY06
budget, GAO said.
The schedule delays "stem from ongoing incidents during operations, environmental
permitting issues, concerns about emergency preparedness, and unfunded requirements,"
GAO said. And the rising costs have caused the military to reallocate funds
in the FY05 budget, Decker said (see related story).
Army and DOD officials asserted at the hearing that they can meet the 2007
45 percent destruction deadline, although they acknowledged that it will
be problematic to meet the 2012 deadline for the Pueblo, CO, and Blue Grass,
KY, sites for both technical and budget reasons.
"I hate to be the skunk at the party," Decker said, but the Pentagon is being
extremely optimistic if it thinks it can destroy 45 percent of the original
stockpile by 2007. The only way that will happen "is if all the stars line
up," he said.
Claude Bolton, Army assistant secretary for acquisition, technology &
logistics, said meeting the destruction deadlines are "a challenge for the
leadership," but by using lessons learned from the Newport and Anniston,
AL, sites, the Army hopes to get ahead of its current schedule.
Decker also raised concerns in his testimony about the lack of a clear definition
of the term "maximum protection," as it relates to the Chemical Stockpile
Emergency Preparedness Program (CSEPP). The program is a joint effort between
the Army and the Department of Homeland Security (DHS) to ensure that communities
near chemical weapons stockpile sites are protected in the case of an accidental
release of agent.
The Army needs to sit down with communities and local emergency preparedness
officials and discuss just what "maximum protection" means, because currently
the boundaries are open, he said.
CSEPP has made significant strides in recent years, helping communities to
reach 95 percent of their benchmark compliance, GAO said. "But despite these
accomplishments, CSEPP costs continue to rise" because state and local communities
continue to identify additional requirements that exceed programmed funding,
especially as the destruction facility in their community is about to start
operations, Decker said. 'This causes fluctuations in data on benchmarks
showing how prepared a community is, and causes the, military to transfer
funds from demilitarization activities to CSEPP, resulting in further delays
to the destruction schedule, he said.
Craig Conklin, chief of the DHS nuclear and chemical hazards branch, agreed
that the definition of "maximum protection" is open ended. But he rejected
Decker's call to better define the term through meetings with local officials.
Coming up with a more stringent definition would take a lot of debate and
may not be worthwhile at this point, he said. And having a flexible definition
can actually help lower CSEPP costs because it allows DHS to use "functional
equivalents" in meeting protection benchmarks, he said.
Communities now have greater buy-in to CSEPP, which has lowered costs, he
said. Conklin gave an example of an original budget of $67 million to protect
sensitive populations near Anniston, but through negotiations, that budget
is now $6.3 million.
Decker maintained that it would be worth a dialogue to improve the CSEPP
process, but Conklin dismissed that idea, saying communities will not view
the threats in a common way, making it difficult for them to reach agreement
on what "maximum protection" would be.