
November
2, 2006
VX destruction ahead of schedule
By Rick Callahan
Associated Press
An Army contractor destroying a deadly nerve
agent stored in western Indiana has neutralized nearly a third of the
stockpile -- most of it after modifications to key pumps that help
destroy the Cold War-era weapon, an Army official said Wednesday.
Other
changes in the works might allow the project to wrap up before the
current target of spring 2008, said Jeff Brubaker, the Army's on site
manager at the Newport Chemical Depot.
As of
Wednesday, more than 30 percent of Newport's original stockpile of
about 250,000 gallons of VX nerve agent had been chemically
neutralized, producing about 462,000 gallons of a caustic wastewater
byproduct called hydrolysate.
That substance
is being stored on site in tanks as the Army awaits word on whether it
can ship it to a DuPont Inc. plant in New Jersey for final treatment
and disposal.
Army contractor Parsons
Technology Inc. began neutralizing Newport's VX -- a single droplet of
which can kill a human in minutes -- in May 2005. But the project's
early stages were plagued by leaks that halted operations for days or
weeks.
Brubaker said the lessons learned
from those incidents enabled engineers to fine-tune the disposal site's
chemical reactors to speed along VX destruction.
In
particular, pumps and piping that circulate heated water and sodium
hydroxide used to destroy the VX were altered to make them less prone
to damage and easier to maintain.
"It's a
simpler configuration, easier to access in protective clothing and it
requires only one-third of the time to repair," Brubaker said. "It's a
significant improvement."
Since the changes, there has been only one spill, which was in March,
and Brubaker said that was caused by human error.
Since
the upgrades were implemented in late 2005 and early this year, Parsons
workers have destroyed more than a quarter of the VX stockpile, he
said. In contrast, by the end of 2005 only about 4 percent of the VX
had been destroyed.
Parsons engineers are
currently weighing two other approaches that could speed up the VX
destruction -- one to reduce how long it takes to neutralize each batch
of VX. The other would cut the reactors' "idle-time" when they are
ready to process VX but held up for some reason.
The Army, which produced its entire supply of VX
at Newport in the 1960s, is required by a 1997 international treaty to
destroy the chemical weapon by 2012.
Craig Williams of the Chemical Weapons Working Group, said he's
heartened that the Newport project is making progress.
"They're
working the bugs out and it's certainly good news for the community
because as the amount of agent decreases, so does the risk," he said.
Last
month, a military spending bill President Bush signed into law included
a provision that requires the Government Accountability Office to
complete an independent cost-benefit analysis before any hydrolysate
can be shipped to a DuPont plant in New Jersey for disposal.
That
requirement likely delays any such shipments until at least March, and
likely longer, Williams said, because the Army still needs permits from
regulators in New Jersey, where opposition to the plans is strong.
Brubaker
said the VX destruction is expected to produce between 1.7 million
gallons and 2 million gallons of hydrolysate, which is being stored on
site in tanks as it is produced.
Newport
spokeswoman Terry Arthur said the Army has obtained permits from the
Indiana Department of Environmental Management to store up to 2 million
gallons of hydrolysate on site.
If
those changes succeed, they could bring the stockpile's destruction to
a quicker end, Brubaker said. The project is currently expected to
reach 50 percent destruction by next spring, with all of the VX gone by
spring 2008.