By
Samantha L. Quigley
American Forces Press Service
ANNISTON, Ala., Aug. 9, 2005 - Local angst over the Anniston Chemical Agent
Disposal Facility here has eased somewhat as the burning of some 2,254 tons
of chemical agent proceeds safely.
Since the first sarin nerve agent-filled M55 rocket was safely destroyed
two years ago, the facility has processed about 80 percent of the munitions
containing sarin housed at the facility, said Mike Abrams, public affairs
officer for the Anniston Chemical Activity and Anniston Chemical Agent Disposal
Facility.
Sarin nerve agent, or GB, makes up about 19 percent of the total agent Anniston
is charged with processing. The M55 rockets that were first destroyed measured
78 inches, weighed 57 pounds and contained nearly one and a half gallons of
nerve agent each.
Of the other agents stored in earth-covered "igloos" at the facility, VX
nerve agent made up 37 percent, and mustard agent made up 44 percent.
To date, the facility, operated by Westinghouse Anniston, a subsidiary of
Washington Demilitarization Company, has destroyed nearly all of the GB-filled
munitions.
Only 105 mm artillery shells are still to be destroyed. On July 23, the
facility began processing those shells, which measure 15 inches long, weigh
32 pounds and contain roughly a fifth of a gallon of GB nerve agent.
Abrams explained that the agency doesn't release numbers of specific munitions
for security reasons. However, he said, destruction of the 105 mm shells is
expected to continue through the end of 2005.
The 105 mm shells are in stark contrast to the 8-inch projectiles the facility
finished processing on July 17. The 8-inch-diameter projectiles were 35 inches
long, weighed 198 pounds and contained nearly two gallons of GB each.
The smaller size of the 105 mm shells will speed the process, Abrams said.
However, he added, if the agent in the weapon has gelled, it cannot simply
be drained out -- and that slows the process.
When all of the GB weapons have been processed, there will be a planned
interruption in the operation schedule to reconfigure the incinerator for
VX weapons. The final phase of operations here will demilitarize the weapons
containing mustard agent.
When the entire stockpile has been processed, the plant will be dismantled
and decontaminated, Abrams said.
"Even though we've only destroyed 15.5 percent of the agent stockpile here,
... we are well on our way to seeing the completion of the disposal program
in Anniston in the year 2010," Abrams said. "That is dependent on continuing
success, and that means a daily focus on safety, not just periodic. (And)
it means that we need the Defense Department and Congress to continue to
fund us."
Storage of chemical weapons on the Anniston Army Depot began in 1961. As
the weapons began to age, they became less stable.
During the 1993 Chemical Weapons Convention in Paris, 130 countries agreed
to terms regarding the treatment of chemical weapons. The resulting treaty
stated that each party would control its stockpile of existing weapons and
never use or prepare to use such weapons for military purposes, according
to the U.S. Chemical Weapons Convention Web site.
Additionally, each party agreeing to the terms of the treaty would take
measures to destroy stockpiles of chemical weapons at home and abroad, as
well as any facilities used to manufacture such weapons.
The convention set a deadline of 2007 for complete compliance. Abrams said
that both Russia and the U.S. will have difficulty meeting that deadline.
Neither, however, wants to invoke the extension that would give countries
until 2012 to complete the task.
How the U.S. will finish on time without invoking the extension is not clear,
as there are other chemical weapons demilitarization locations in the country
that have not yet been brought on line, Abrams said.
ANAD and the ANCDF will not rush things, because safety is the bottom line,
Abrams said. The facility has collected a "safe work hour" total of more than
7.2 million hours. That means that there were no incidents that caused a
lost day of work or a hospital visit in that amount of time.
"My boss refuses to impose a hard, fast goal ... on the systems contractor,"
Abrams said. "He insists that if the operators inside this plant working with
these very dangerous weapons have a requirement to meet that that could lead
to a ... careless mistake.
"Instead, he insists that we focus on safety. Everything we do is done 'safety
first.'"
As an example of that philosophy, a July 28 lightning strike near the facility
has made the ANCDF pause its schedule to evaluate whether there was any
effect to the equipment. Abrams said he expects the plant to resume processing
105 mm artillery shells soon.
That safety culture is for the benefit of all involved in incinerating part
of the country's aging stockpile and the surrounding community.
"Now we've had almost two years of very successful operations, and during
these two years with positive media reports, without any major problem a the
site ... all of our success has provided the community with the reassurance
that we can do our work, we can do it safely, and our ultimate goal of safely
destroying all of the weapons can be realized."